Etobicoke Retail Shell: Commercial Boarding, Level 4 Finish & ProMar Seal

By Bottega Painting & Finishes — Toronto

Starting from a gutted Lake Shore commercial shell framed by 1&Co, partitions received condition-matched CGC UltraLight Pro, Mold Tough, and 5/8 in. Type X Firecode boards. Seams were finished with a custom CGC Sheetrock 90 and all-purpose base blend, skimmed with machine-grade compound, power-sanded to continuous planes, caulked at interior corners, and sealed with Sherwin-Williams ProMar primer—delivering a paint-ready retail and washroom envelope.

Taking over after 1&Co completed the structural framing, our crew handled the complete drywall boarding, taping, compounding, and priming scope across complex corridor runs, bulkheads, and masonry openings. After hanging and trimming the gypsum panels, we embedded paper tape and corner beads along every transition. To build strong, low-shrinkage seams with optimal workability, we ran two fill coats using a custom blend of CGC Sheetrock 90 setting-type drywall compound and ready-mixed all-purpose compound (Red Box), topped with a tight skim coat of machine-grade finishing compound (Yellow Box). Surfaces were machine- and pole-sanded under work lighting, interior corners were detailed with paintable acrylic caulk, and the entire substrate was sealed with Sherwin-Williams ProMar 200 Primer and point-up touch-ups for a dead-flat, paint-ready handoff.

Location
Etobicoke, Toronto
Year
2026
Duration
6 days

Scope of work

  • Commercial Drywall & Interior Finishing
  • Drywall Installation and Finishing
  • Taping, Mudding & Sanding
  • Drywall Patching & Surface Prep
  • Interior Primer Application
  • Commercial Store Renovation
  • Drywall Board Hanging
  • Level 4 Joint Taping
  • Paper-Faced Corner Beads
  • Fire-Rated Boarding (Type X)
  • Washroom Green Board
  • High-Build PVA Primer
  • Condition-matched gypsum boarding on wood studs
  • 5/8 in. Type X Firecode party-wall assemblies
  • Mold Tough moisture-resistant washroom boarding
  • FibaFuse taping with multi-coat All Purpose-Lite
  • Machine sanding to Level 4 continuous planes
Storefront
Bottega Painting & Finishes

Etobicoke Retail Shell: Commercial Boarding, Level 4 Finish & ProMar Seal

Commercial Drywall & Interior Finishing · Etobicoke, Toronto · October 2026

Starting from a gutted Lake Shore commercial shell framed by 1&Co, partitions received condition-matched CGC UltraLight Pro, Mold Tough, and 5/8 in. Type X Firecode boards. Seams were finished with a custom CGC Sheetrock 90 and all-purpose base blend, skimmed with machine-grade compound, power-sanded to continuous planes, caulked at interior corners, and sealed with Sherwin-Williams ProMar primer—delivering a paint-ready retail and washroom envelope.

Area
2100
Walls & Ceilings
Time on site
6 days
Finish
Level 4

The work

Taking over after 1&Co completed the structural framing, our crew handled the complete drywall boarding, taping, compounding, and priming scope across complex corridor runs, bulkheads, and masonry openings. After hanging and trimming the gypsum panels, we embedded paper tape and corner beads along every transition. To build strong, low-shrinkage seams with optimal workability, we ran two fill coats using a custom blend of CGC Sheetrock 90 setting-type drywall compound and ready-mixed all-purpose compound (Red Box), topped with a tight skim coat of machine-grade finishing compound (Yellow Box). Surfaces were machine- and pole-sanded under work lighting, interior corners were detailed with paintable acrylic caulk, and the entire substrate was sealed with Sherwin-Williams ProMar 200 Primer and point-up touch-ups for a dead-flat, paint-ready handoff.

  • Clean drywall boarding and bead detailing around exposed brick openings, long corridors, and ceiling bulkheads.
  • Two fill coats blending CGC Sheetrock 90 setting-type compound with ready-mixed all-purpose mud for superior bond, minimal shrinkage, and crack resistance.
  • Final coat of Yellow Box machine finishing mud, leveled with powered and pole sanders under critical work lighting.
  • Full perimeter and interior angle sealing with paintable acrylic gap filler prior to priming.
  • High-build drywall primer-sealer followed by targeted spot-skimming and touch-ups for a uniform, paint-ready substrate.

Scope of work

  • Commercial Drywall & Interior Finishing
  • Drywall Installation and Finishing
  • Taping, Mudding & Sanding
  • Drywall Patching & Surface Prep
  • Interior Primer Application
  • Commercial Store Renovation
  • Drywall Board Hanging
  • Level 4 Joint Taping
  • Paper-Faced Corner Beads
  • Fire-Rated Boarding (Type X)
  • Washroom Green Board
  • High-Build PVA Primer
  • Condition-matched gypsum boarding on wood studs
  • 5/8 in. Type X Firecode party-wall assemblies
  • Mold Tough moisture-resistant washroom boarding
  • FibaFuse taping with multi-coat All Purpose-Lite
  • Machine sanding to Level 4 continuous planes
  • High-build KILZ PVA primer seal on walls/ceilings
  • Rough-in cutouts and penetration detailing
  • Spot patching and paint-ready commercial handover

Materials

  • Standard interior gypsum boards, paper joint tape, and corner beads
  • Custom blend of CGC Sheetrock 90 Setting-Type Drywall Compound (blue bag) + Ready-Mixed All-Purpose Joint Compound (Red Box)
  • Machine-Grade Finishing Compound (Yellow Box Machine Mud)
  • Paintable acrylic latex caulk (interior corners and perimeter transitions)
  • Sherwin-Williams ProMar 200 Zero VOC Interior Latex Primer (commercial-grade drywall sealer)
  • Powered drywall sanders, pole sanders, and critical work lighting

Step by step

  1. 1

    Initial Site Conditions

    Baseline site documentation capturing existing layouts, unfinished corridors, and rough masonry openings prior to our scope of work.

  2. 2

    Structural Framing Inspection

    Reference documentation of the wood and steel framing completed by 1&co contractors, inspected for alignment and readiness ahead of boarding.

  3. 3

    Drywall Boarding & Bead Installation

    Gypsum boards were hung, fastened, and trimmed across walls, bulkheads, and brick openings, followed by paper tape and corner bead installation along all transitions.

  4. 4

    Compounding, Skimming & Machine Sanding

    Taped seams received two fill coats blending CGC Sheetrock 90 setting-type drywall compound with ready-mixed all-purpose compound, followed by a skim coat of machine-grade finishing compound. Surfaces and upper corners were then machine- and pole-sanded until flat and continuous under work lighting.

  5. 5

    Acrylic Corner Sealing & ProMar Priming

    Prior to priming, all interior corners and perimeter transitions were sealed with paintable acrylic caulk for crisp, crack-resistant lines. Sherwin-Williams ProMar 200 Zero VOC Primer was then applied across all surfaces to seal the fresh drywall, equalize porosity, and reveal any minor imperfections under raking light.

  6. 6

    Point-Up & Final Surface Prep

    Highlighted pinholes and minor surface marks were spot-skimmed, lightly hand-sanded, and re-primed to deliver a uniform, paint-ready finish.

More photos

Want work like this?

CallWhatsApp

Bottega Painting & Finishes

Albi · Painting, taping and drywall finishes

I'm Albi of Bottega Painting & Finishes, based in Toronto. We take on interior and exterior painting, cabinet and trim work, drywall finishing and repairs, as well as full renovations for homes and commercial spaces. Careful prep, clean finishes, and a tidy job site are how we work—with clear communication and realistic schedules.

  • Serving Toronto, within 50 km
See the full page
Bottega Painting & FinishesProjects
Powered byCantiko
  • High-build KILZ PVA primer seal on walls/ceilings
  • Rough-in cutouts and penetration detailing
  • Spot patching and paint-ready commercial handover
  • Results

    • Clean drywall boarding and bead detailing around exposed brick openings, long corridors, and ceiling bulkheads.
    • Two fill coats blending CGC Sheetrock 90 setting-type compound with ready-mixed all-purpose mud for superior bond, minimal shrinkage, and crack resistance.
    • Final coat of Yellow Box machine finishing mud, leveled with powered and pole sanders under critical work lighting.
    • Full perimeter and interior angle sealing with paintable acrylic gap filler prior to priming.
    • High-build drywall primer-sealer followed by targeted spot-skimming and touch-ups for a uniform, paint-ready substrate.

    Materials

    • Standard interior gypsum boards, paper joint tape, and corner beads
    • Custom blend of CGC Sheetrock 90 Setting-Type Drywall Compound (blue bag) + Ready-Mixed All-Purpose Joint Compound (Red Box)
    • Machine-Grade Finishing Compound (Yellow Box Machine Mud)
    • Paintable acrylic latex caulk (interior corners and perimeter transitions)
    • Sherwin-Williams ProMar 200 Zero VOC Interior Latex Primer (commercial-grade drywall sealer)
    • Powered drywall sanders, pole sanders, and critical work lighting

    On site

    • Interior view of an active renovation site showing exposed wooden plank walls, ceiling beams, and metal stud wall framing. Debris, cables, tools, and construction materials cover the dirt floor. Fluorescent lights are visible in an adjacent room through the open framing.
    • Interior view during active renovation showing exposed wooden ceiling beams, brick walls, and new wall framing. A white toilet sits in the foreground amid debris and a gray tarp. Work lights illuminate background framing and a ladder. Floor is concrete with scattered construction materials.
    • Interior view of an unfinished commercial space during renovation. Wooden wall framing and metal studs form new openings, with exposed ceiling joists, wiring, and a dirt floor. A ladder leans against a framed doorway, tools and materials are scattered throughout, and a bright work light illuminates the central area.
    • Interior view of a basement during renovation showing exposed wooden floor joists and ceiling beams, partial wall framing, brick walls, a standalone white toilet, Rockwool insulation bags, a black tarp, and construction debris on the concrete floor.
    • Large open commercial space during demolition with exposed wooden ceiling beams and joists, brick wall on right, concrete floor covered in debris, wood scraps and cables. Partial wood framing and metal studs visible, work table and ladder in background, open areas to adjacent rooms.
    • Interior view of an ongoing commercial renovation showing exposed ceiling joists, a green structural beam, partial wooden and metal framing, a black debris cart, extension cords, a yellow reel, scattered materials, and an open doorway to a brighter adjacent space. Left wall has vertical wood sheathing; floor is concrete with dust and construction debris.
    • Interior view of an unfinished basement space during renovation. Exposed wooden wall studs, torn drywall and insulation, scattered wiring and pipes, hanging temporary light, and construction materials including metal tracks and cardboard boxes on the dirt floor. Debris and old building remnants visible throughout the dim space.
    • Interior view of an unfinished basement shop space with exposed wooden stud walls, peeling paint, dirt floor, overhead fluorescent work light, electrical wiring, black debris bin, sawhorse, and construction materials scattered throughout. The room appears to be in an early renovation or demolition phase.
    • Wide view of an active construction site inside a building with exposed wooden wall studs and ceiling joists. Temporary work lights illuminate the space. A portable workbench on sawhorses sits in the foreground with power tools visible. Concrete floor and open framing indicate ongoing structural work.
    • Unfinished interior space showing exposed wooden wall studs, OSB sheathing on walls and floor, a gray door open to an outdoor area with trees and fencing, a tripod work light, and visible electrical cords on the subfloor.
    • Interior view of an active renovation showing newly erected wooden wall framing dividing a space with exposed brick walls, ceiling joists, and a concrete floor. Wood offcuts lie scattered on the floor and a bright temporary work light hangs from above.
    • Exposed wooden stud framing for interior walls with insulation visible on left side, OSB subfloor, and open doorway to exterior. Construction debris and wiring present on floor during active renovation.
    • Interior view of an active renovation showing exposed wooden wall studs, ceiling joists, and OSB sheathing. Concrete floor displays VaporSeal text. Red cables, a bright work light on a stand, and scattered construction materials are visible throughout the space.
    • Unfinished room showing exposed wooden 2x4 wall studs, OSB subfloor, work light on tripod, red level tool, coiled extension cord, and plastic sheeting. Construction materials and debris visible throughout the space.
    • Interior view of an unfinished space with exposed wooden wall studs, ceiling joists, and floor. A bright work light illuminates the left side. Debris including wire and materials visible on the subfloor. Multiple framed openings suggest doorways or rooms in progress.
    • Empty interior room during renovation showing white drywall panels installed on all walls with visible horizontal and vertical seams, screw heads, and electrical outlet boxes. Bare concrete floor with red markings and a black cable visible along the right wall. White ceiling with multiple circular cutouts for recessed lighting.
    • Interior view of a room during renovation showing white drywall on walls and ceiling with green moisture-resistant board at base, multiple recessed lighting cutouts in ceiling, unfinished floor, and open doorways to adjacent spaces.
    • Room under renovation with white drywall panels installed on walls, exposed wooden ceiling joists and framing on left side, concrete subfloor, and scattered construction materials including a white bag in foreground.
    • Interior view of an unfinished space showing white drywall panels installed on walls with visible seams and screws, exposed ceiling joists with insulation and electrical cables, and a light-colored tiled floor. Blue painter's tape markers are visible on the floor and walls.
    • Interior view of a room during renovation with white drywall panels installed on walls, some seams visible. Ceiling is open showing wooden joists and insulation. Concrete floor has construction debris, orange spray paint markings, and a blue tape marker. Electrical boxes and wires are present on walls.
    • Unfinished drywall installation showing two adjacent walls with visible screw holes, vertical seams, and a white PVC pipe protruding through the right wall. Green material visible at the top corner edge. Corner joint and wall framing details are exposed.
    • Empty interior space with exposed ceiling panels and recessed lighting cutouts, unpainted drywall walls, concrete floor scattered with debris, open white door leading outside, and plywood sheathing on the left wall. Natural light enters from the doorway.
    • Interior view of a room during renovation showing white drywall panels installed on ceiling and upper walls. Visible panel seams, screw fasteners, and two circular openings in the ceiling for fixtures or vents. Walls and ceiling remain unpainted with no finishing materials applied.
    • Worker using a powered long-handled drywall sander on a white wall inside a room with exposed ceiling insulation and wooden framing visible above.
    • A worker in a white t-shirt uses a long-handled electric sander on a white drywall wall in an unfinished room. The ceiling shows exposed joists and insulation with blue plastic sheeting visible.
    • A worker's hand holds a yellow and black extendable pole with a sanding head pressed against the upper wall and ceiling corner. The room shows white painted drywall surfaces, an exposed red brick wall section with an open doorway, and visible shadows from the pole and worker.
    • Interior view of a room during drywall finishing. Walls and ceiling show taped seams with multiple coats of joint compound applied over drywall panels. Some areas have thicker mud coverage while others remain partially finished. A small damaged hole is visible near the base of the wall. The space appears to be a commercial shop renovation.
    • Long empty corridor with white drywall panels installed on walls, visible seams and patches. Ceiling is open showing wooden joists, white insulation batts, and blue vapor barrier. Concrete floor with red markings and construction debris. Distant room visible at end of hallway with partial drywall.
    • Interior room under renovation with drywall installed and taped on ceiling and walls, exposed wooden framing on left side, subfloor visible, step ladder, orange shop vacuum, and work light on tripod present.
    • Empty commercial space with white walls showing drywall patches, electrical boxes, and unfinished surfaces. Gray door installed on back wall, concrete floor, and portable work light on floor with power cord visible. Lighting is dim with shadows cast on walls.
    • Interior view of an unfinished commercial space showing white drywall walls with gray joint compound patches and tape. An open doorway reveals an adjacent room with exposed framing and construction materials. Concrete floor with extension cords and minor debris visible. Bright light source creates lens flare in lower left.
    • Worker using a yellow extension pole with a flat blade to work the top edge of an exposed brick doorway or window in a white-painted room. Shadows of the pole and operator are cast on the smooth white wall and ceiling.
    • Worker in black shirt holds a white rectangular electrical device against a plain wall while a bright work light creates strong shadows and highlights. The scene shows hands positioning the item near an existing opening, indicating active installation work.
    • White painted ceiling surface showing hand-drawn pencil markings including a lightning-bolt shape, a circle, and curved lines. Exposed brick and wooden framing visible in the lower right corner, indicating an unfinished opening or transition area.
    • Interior view of a renovation in progress showing a worker using a paint roller on an extension pole to apply white primer to a textured drywall wall. A bright Husky LED work light on a tripod illuminates the corner, highlighting the fresh coat. The ceiling is unfinished with exposed framing and the floor is bare concrete. Partial view of the worker in dark clothing on the right side.
    • A worker wearing a black long-sleeve shirt and black glove holds a paint roller on an extension pole, applying white paint to a ceiling. Some ceiling sections show unfinished patches or prior texture.
    • Interior room under renovation showing white drywall panels on walls with visible seams and compound. Exposed ceiling with insulation, wooden joists, and black vapor barrier tape. Floor holds painting tools including buckets, paint tray with roller on yellow stand, cordless drill, and a propane heater. Concrete floor partially covered with drop cloths.
    • Gloved hand using a yellow-handled paint roller to apply white paint to a ceiling during an interior renovation. Visible motion and paint mist indicate active painting work.
    • Large empty commercial space during active renovation. White drywall walls with blue painter's tape, multiple unfinished doorways and openings, exposed recessed lighting cutouts in ceiling, dirty concrete floor with debris, stains, extension cords, spray foam gun, and a white bucket visible.
    • Interior view of an unfinished commercial space during renovation. White drywall panels cover the walls with blue painter's tape, exposed electrical boxes, and plumbing rough-ins including copper pipes. Ceiling shows exposed wooden joists, insulation, and vapor barrier. Concrete floor has extension cords and debris. Doorway leads to adjacent unfinished room with window.
    • Interior view of a commercial space during renovation. Exposed ceiling with insulation and wooden joists, white drywall walls, concrete floor with scattered extension cords. Work table with tools and materials positioned along the wall. Door visible in background.
    • The rendering shows a partial 3D floor plan model of the space with orange and green highlighted wall segments indicating existing or proposed construction elements. White and gray forms represent the main room volumes, door openings, and structural boundaries in an unfinished layout.
    • Long narrow space with wood stud framing installed along both side walls on OSB subfloor. Exposed ceiling joists, temporary lighting, and wiring are visible overhead with a contractor standing near a central workbench setup containing power tools and materials.